American Transmission Systems, Inc. (ATSI), a subsidiary of FirstEnergy Corp., is proposing to construct a 138,000 volt power transmission line passing through Thompson, Montville and Huntsburg townships. The proposal is causing much concern on the part of residents due to the locations of the two proposed routes.
 
Geauga~Link is offering this discussion space to serve as medium for the sharing of ideas and a source of definitive information. This discussion space is provided primarily for members of the affected communities and others having a direct interest in the topic, but participation is not restricted in any way other than the expectation that users of this service will respect the copyrights of others, avoid long diatribes and "off topic" postings, and observe the general dictates of good manners.

Subscribe to get & post, or stop messages by email Subscribe
All messages            179-194 of 194  163-178 >>
Who | When
Messagessort recent-bottom   
Post a new message
 
broodscer  194
08-26-2008 12:07 AM ET (US)
I'm new here, just wanted to say hello and introduce myself.
Geauga~LinkPerson was signed in when posted  193
08-21-2008 02:51 PM ET (US)


Media Coverage Update - 45


Geauga County Maple Leaf, August 21, 2008

Report favors Route 528 path for power line


.
Jim GalmPerson was signed in when posted  192
08-18-2008 11:15 PM ET (US)
Edited by author 08-18-2008 11:34 PM
ADJUDICATORY HEARING DATE CHANGED

On August 7, 2008, the CARE legal team filed a petition to continue the adjudicatory hearing, i.e., postpone it to a later date. The legal team asked for an immediate ruling. Click here to view the entry on the case docket.

The motion and memorandum in support did the job. On August 14, 2008, Judge Stoneking entered an order that continued the adjudicatory hearing until Tuesday, September 16, 2008. Click here to view the entry on the case docket. It is my understanding that the hearing is expected to last nine days, thus the complete hearing is planned to run from September 16 - 19 and September 22 - 26.

According to the order, the case procedural schedule is now as follows:

Case Status Conference: August 18, 2008
Local Public Hearings: August 27 & 28, 2008
Discovery Completion: August 29, 2008
File Direct Testimony: September 8, 2008
Local Public Hearing: September 10, 2008
File Staff Testimony: September 16, 2008
Adjudicatory Hearing: September 16, 2008

The adjudicatory hearing is scheduled to begin at 10:00 a.m., at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, 11th floor, Hearing Room F, Columbus, Ohio 43215-3793. Click here for a map showing the PUCO building

Visit CARE’s web site.
Geauga~LinkPerson was signed in when posted  191
08-18-2008 09:38 PM ET (US)


Media Coverage Update - 44


The News-Herald, August 18, 2008

Chardon council backs off endorsing power line


.
Geauga~LinkPerson was signed in when posted  190
08-15-2008 05:07 PM ET (US)
Edited by author 08-15-2008 05:08 PM
OPSB Calendar

OPSB Adjudicatory hearing rescheduled to September 16



The most recent version of the OPSB Calendar indicates that the start of the adjudicatory hearing has been rescheduled from Tuesday, September 2, 2008 to Tuesday, September 16, 2008, at 10:00 a.m., at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, 11th floor. Hearing Room F, Columbus, Ohio 43215

More information regarding the proposed transmission line is available at www.opsb.ohio.gov.

.
Geauga~LinkPerson was signed in when posted  189
08-15-2008 04:56 PM ET (US)


Media Coverage Update - 43


The Plain Dealer, August 12, 2008

Power lines would be best in eastern Geauga County, report says


.
Geauga~LinkPerson was signed in when posted  188
08-15-2008 04:50 PM ET (US)


Media Coverage Update - 42


The News-Herald, August 8, 2008

Geauga power line hearing set for Sept. 10


.
Jim GalmPerson was signed in when posted  187
08-10-2008 05:04 PM ET (US)
Edited by author 08-10-2008 05:05 PM
COMPLETE SET OF SCANNED MAPS IS NOW ONLINE

Many individuals have asked to have the color route maps published in the application available online. Here they are!

Click here to visit the complete set. If the link fails, browse to http://www.huntsburg.org/firstenergy/ and follow the page index to "Maps of proposed routes in the application."

The cross country route is complete and online. The Clay Street route is almost finished and will be online shortly. Check back soon.

Visit CARE’s web site.
Geauga~LinkPerson was signed in when posted  186
08-07-2008 04:29 PM ET (US)
Edited by author 08-07-2008 04:30 PM


Media Coverage Update - 41


Geauga County Maple Leaf, August 7, 2008

Transmission line controversy to take center stage


.
Geauga~LinkPerson was signed in when posted  185
08-07-2008 03:55 PM ET (US)
OPSB release

OPSB schedules third Geauga County transmission line public hearing



COLUMBUS, OHIO (Aug. 6, 2007) – The Ohio Power Siting Board (OPSB) today scheduled an additional local public hearing to give consumers an opportunity to express their views regarding American Transmission Systems, Inc.’s (ATSI) application to construct a 138-kilovolt electric transmission line in Geauga County.

The third local public hearing is scheduled as follows:
Wednesday, Sept. 10, 2008 at 6 p.m.
Huntsburg Town Hall, Second Floor
16534 Mayfield Road
Huntsburg, Ohio

The OPSB previously scheduled two additional local public hearings. These hearings are set for:
Wednesday, Aug. 27, 2008, at 4:30 p.m.
Ledgemont Elementary – Middle School Gymnasium
16200 Burrows Road
Thompson, Ohio
Thursday, Aug. 28, 2008, at 1:30 p.m.
Huntsburg Town Hall, Second Floor
16534 Mayfield Road
Huntsburg, Ohio

More information regarding the proposed transmission line is available at www.opsb.ohio.gov.

.
Jim GalmPerson was signed in when posted  184
08-04-2008 01:12 AM ET (US)
Edited by author 08-04-2008 01:22 AM
CITIZENS ADVOCATING RESPONSIBLE ENERGY
CARE
REGULAR MEETING TO BE HELD ON THURSDAY, AUGUST 7, 2008 AT 7:30 PM
MONTVILLE COMMUNITY CENTER


Citizens Advocating Responsible Energy (CARE) will hold its next regular meeting on Thursday, August 7, 2008, at 7:30 PM at the Montville Community Center. The Montville Community Center is located at 9755 Madison Road, Montville, Ohio 44064, just south of US-6. Click here for a map.

Everyone interested in learning more about The Geauga County - 138kV Transmission Line Supply Project or interested in learning about or supporting CARE is invited to attend.

There are so many main topics that they barely fit into one meeting:
  • Legal Update.
  • The upcoming PUBLIC HEARINGS on August 27 and 28.
  • CARE's witnesses for the ADJUDICATORY HEARING.
  • The CARE Silent Auction Fundraiser.
While on the topic of fundraisers, bring your ideas and items for the

CARE Silent Auction
Saturday, September 13, 2008
It's not too early to start selling tickets to this wonderful event.

Also, the date of the September CARE regular meeting has been changed by one week to Thursday, September 11, 2008. The original date conflicted with the Adjudicatory Hearing in Columbus.

Please spread the word to everyone you know that might be interested in learning about, supporting or joining CARE.
Jim Galm  183
07-18-2008 01:02 AM ET (US)
Edited by author 07-18-2008 01:03 AM
SAVE THIS DATE:
SEPTEMBER 27, 2008
for the
CARE CLAM BAKE FUNDRAISER


Citizens Advocating Responsible Energy (CARE) is planning a CLAM BAKE fundraiser for Saturday, September 27, 2008, at the Montville Community Center. Click here for a map. This event is being planned by THE DIFRANCO FAMILY, creators of all previous fantastic CARE fundraising dinners. More details will be posted when they are available.

Sure, there are lots of clam bakes in the fall -- but this is the one to NOT MISS. The DiFranco clam bakes are LEGENDARY, guaranteed to be the highlight of the clam bake season.

Visit CARE’s web site.
Geauga~LinkPerson was signed in when posted  182
07-13-2008 05:19 PM ET (US)


Media Coverage Update - 40


News-Herald, July 12, 2008

Grendell back on the line


.
Geauga~LinkPerson was signed in when posted  181
07-13-2008 05:15 PM ET (US)


Media Coverage Update - 39


The Star Beacon, June 25, 2008

CARE group early intervenor in FirstEnergy power line case


.
Geauga~LinkPerson was signed in when posted  180
07-13-2008 05:12 PM ET (US)
Edited by author 07-13-2008 05:20 PM


Media Coverage Update - 38


The Star Beacon, June 23, 2008

What a shock!

Orwell Village enters as intervenor in CEI power case


.
Geauga~LinkPerson was signed in when posted  179
07-13-2008 05:07 PM ET (US)
Edited by author 07-13-2008 05:10 PM


Media Coverage Update - 37


News-Herald, June 19, 2008

FirstEnergy passes on Chardon trail


.
RSS link What's this?
All messages            179-194 of 194  163-178 >>
QuickTopicSM message boards
Over 200,000 topics served
Learn more Frequently asked questions  Acknowledgements
What they're saying about QuickTopic
 Questions, comments, or suggestions? Contact Us
Read our use policy before beginning. We value your privacy; please read our privacy statement.
Copyright ©1999-2008 Internicity Inc. All rights reserved.